EAST PINE PUMP STATION

Existing pump station  electrical and controls removed from operation and set up into temporary trailer with a motor control center and a main control panel to allow full operation of facility while upgrades made:
Demolition of existing equipment  inside existing pump station facility
New housekeeping curbs poured, new motor control center installed.
Three new VFD’s, new HVAC, new instrumentation and controls installed
Electrical and controls transferred back to existing pump station and tested.

General Contractor: Burke Electric

Owner: King County Waste Water Division